We’re forwarding the following update from the 47th Ward Office for those who may not have received it directly.

The Department of Water Management is starting work replacing 1,300 of water main beneath Hutchinson (Greenview to Clark) and Greenview (Berteau to Cullom). The water main is the large pipe that runs along the street and brings water to each building’s individual service line. The existing water main dates back to the 1890s. This project will be an opportunity for DWM to replace the water main, replace any existing lead service lines connecting to it, and fully repave all three blocks once the project is complete. This project was identified over the years based on the age of the main and the history of breaks and leaks impacting it.
Start Date: Crews will start moving equipment to the area this week, with digging beginning next week.
Expected Duration of Project: 3 months (July completion), followed by asphalt and concrete restoration.
Parking impacts: 7am-3:30pm on weekdays – no access to or parking on the street. Parking will be available at all other times. Crews will work to accommodate special deliveries, disabled residents, etc.
Water Shutoffs: Crews will strive to provide 5 days’ notice ahead of any scheduled service interruptions. Some emergency repairs may take place (old pipes tend to crack as they are being worked on). These service interruptions are not expected to impacted buildings that are not on the directly impacted blocks.
Water Main Replacement Process: Two separate crews will trench to install a new water main a few feet from the old one. They will work:
- On Hutchinson: Starting at Clark, working west.
- On Greenview: Starting at Cullom, working south.
Throughout the whole project DWM will aim to be minimally invasive, using trenchless technology and working around existing trees wherever possible.
Best,
Joshua Mark
Chief of Staff